Annex B: CIL Instalment Policy
The Community Infrastructure Levy will be implemented from 01 February 2026.
The Community Infrastructure Levy ratesare required to be paid to the Council throughthe following instalments following the provision of a CIL Demand Notice issued by the Council.
|
Overall CIL liability |
Payment instalments |
|
Less than £20,000 |
Payment in full within 60 days |
|
£20,000 - £99,999 |
50% paid within 90 days Further 50% paid within 180 days |
|
£100,000 - £499,999 |
25% at 90 days 25% at 180 days 50% at 360 days |
|
£500,000 or more |
25% at 90 days 25% at 240 days 50% at 480 days |